Completed Works & Projects

Council has an on-going program of capital works and upgrades to buildings, parks, playgrounds, and roads across the district. Below are some projects and works that have recently been completed.

Fulwood Ave intersection upgrade drone image taken 29 July 2026

Tintinara Intersection Upgrade – Northcott Terrace & Fulwood Avenue

The Tintinara Intersection Upgrade improved safety, traffic flow and access for both local and freight vehicles at the intersection of Northcott Terrace and Fulwood Avenue.

The project involved reconfiguring the existing layout into a modified T-intersection, along with pavement, drainage and footpath improvements, line marking and new signage.

These upgrades have enhanced the functionality of a key local transport route while providing a safer experience for all road users.

Railway Tce Tailem Bend Carpark Redevelopment drone image taken 28 August 2026

Railway Terrace, Tailem Bend - Carpark Redevelopment

The Railway Terrace Carpark Redevelopment has enhanced one of Tailem Bend’s key town centre parking areas, delivering improved drainage, safer pedestrian access, upgraded accessibility and a more efficient parking layout.

Located between the Station Master’s House and the RSL Memorial, the project included new kerbing, drainage upgrades, asphalt surfacing, footpath connections, DDA-compliant pram ramps and landscaping improvements.

The redevelopment has improved both the functionality and visual appeal of the Railway Terrace precinct, creating a safer and more welcoming space for residents and visitors.

Changing Places Coonalpyn Building

Coonalpyn Changing Places Toilet

The Coonalpyn Changing Places Toilet project has delivered a modern, inclusive public amenity designed to support people with high support needs and their carers.

The new facility includes a fully accessible Changing Places toilet, DDA-compliant amenities, ambulant toilets and standard unisex toilets, helping to improve accessibility for residents and visitors travelling through the region.

The project aligns with Council’s Disability Access and Inclusion Plan and was delivered with funding support from the Australian and South Australian Governments through the Accessible Australia initiative.

Once completed, the old toilet block was removed and the area returned to open green space.

Carcuma road upgrade progress photo - Feb 2025

Carcuma Road Upgrade

The Carcuma Road Upgrade has delivered significant improvements to one of the district’s key freight routes, enhancing access to the Thomas Foods International (TFI) Feedlot and improving road safety and efficiency for heavy vehicles.

The project involved widening 13 kilometres of road and sealing an additional 15 kilometres from the Dukes Highway through to the Council boundary north of Tintinara.

The upgraded road now features sealed traffic lanes and shoulders, improved road geometry, and is designed to accommodate 36-metre A-double truck combinations.

Funded through the Special Local Roads Program, Local Roads and Community Infrastructure Program, and Coorong District Council, the project supports regional industry, freight movements and long-term economic development in the district.

Coorong Community Skate Park Official Opening - 17-4-23 - Group Photo in the Bowl

Coorong Community Skate Park

Completed in April 2023 and officially opened on 17 April 2023, the Coorong Community Skate Park delivered a modern recreation facility within the Meningie Oval precinct, providing a safe and welcoming space for skateboarding, scooters and BMX riding.

The project was driven by local young people, whose passion and advocacy helped bring the skate park to life, with the Meningie Skate Park Committee recognised with the Mayor’s Award at the 2022 Australia Day Awards.

Jointly funded through the AAustralian Government's Local Roads and Community Infrastructure Program (LRCIP) and Coorong District Council, the skate park supports active recreation, social inclusion and community wellbeing while catering for a range of ages and skill levels.

Wellington East Reserve Transformation Project - From Above

Wellington East Reserve Transformation Project

Completed in June 2022, the Wellington East Reserve Transformation Project was funded through the Australian Government’s Murray-Darling Basin Economic Development Program.

The project transformed the reserve into an attractive riverside recreation space, delivering new public toilets, barbecue facilities, shelters, pathways, landscaping, seating, bike storage and improved beach access near the boat ramp and pontoon.

The upgrades have enhanced the reserve as a popular destination for both residents and visitors enjoying the Lower Murray region.

There is opportunity for further transformation of the reserve in future, including expansion of the pathway to wind its way further into the reserve, a nature play space, relaxed seating and further landscaping that compliments the marina’s water views. These elements will be considered as future funding opportunities present.

Meningie Lions Park Revitalisation

Completed in 2024, the Meningie Lions Park Revitalisation project upgraded the park with new shelters, picnic settings, accessible pathways and a modern outdoor gym.

The improvements created more open space for community events while enhancing accessibility, recreation opportunities and the overall visitor experience.

Coorong Community Skate Park Shelter

Project Summary

Construction of the Coorong Community Skate Park was completed in April 2023. The Coorong Community Skate Park Committee (formed by a group of students from Meningie Area School and supported by staff and parents) have since raised over $34,000 to construct a Picnic Shelter next to the skate park (to house two new picnic tables). The shelter will be connected to the existing skate park and playground by a new section of footpath.

Project Status

Works took place for the installation of the new Picnic Shelter at the Coorong Community Skate Park on Wednesday, 21 February 2024 and were completed on Friday, 15 March 2024.

Mayor Paul Simmons with students of the Tailem Bend Primary school with the new fence at the Tailem Bend Train Park

Tailem Bend Train Park Upgrade

Completed in 2023, the Tailem Bend Train Park Upgrade improved safety and accessibility through the replacement of the playground’s perimeter fencing and retaining wall adjacent to Railway Terrace.

Funded through the Australian Government’s Local Roads and Community Infrastructure Program, the project enhanced one of the town’s most popular family recreation spaces.

The project was officially celebrated with students from Tailem Bend Primary School, whose advocacy helped bring the need for the upgrade to Council's attention.

Poltalloch Road completed

Poltalloch Road Reconstruction

Completed in 2024, the Poltalloch Road Reconstruction Project delivered the rehabilitation of 11.8 kilometres of road through pavement reconstruction, cement stabilisation and sealing works.

Delivered over four stages, the project improved road quality, safety and reliability for road users. Funding was provided through the Australian Government’s Local Roads and Community Infrastructure Program, the Special Local Roads Program and Coorong District Council.

AMPOL Service Road, Princes Hwy Tailem Bend After Works Completed

Princes Highway Service Road Reconstruction Works (AMPOL, Tailem Bend)

On Monday, 11 September 2023 reconstruction of the Princes Highway Service Road (Adjacent to AMPOL), Tailem Bend commenced.

This project sees replacement of the road pavement adjacent to the AMPOL service station along with a completely new asphalt seal to the entire service road. In addition to the pavement and seal works, there has been a cleanout of the stormwater swale drain, upgrades to some localised underground stormwater piping, kerbing to formalise the mid-block entrance, upgraded signage and line marking to provide better traffic flow management.

Construction of the project will took approximately 4 weeks to complete.

Meningie Aerodrome Fencing Project

Council recently completed an upgrade to the perimeter fencing of the Meningie Aerodrome. The project was jointly funded by Council and the Regional Airports program funded by the Federal Government. The Aerodrome is now almost completely fenced using 1.5m high vermin proof fencing as well as providing a clear access path for future fence line maintenance.

To address  flooding issues in Allen, Edward, and Falkner Street in Meningie, Council installed a pumping chamber at the Falkner Street main drain to assist in the rate of drainage flow. Previously, the main drain on Falkner Street was a wet system, which remained 80% full all the time. The installation of the new pumping chamber will pump the water from the main drain to keep it dry, increasing its capacity during heavy rain events.

Works occurred during May 2023 which involved removing reeds, widening the existing open channel and shaping the spillway to the main drain at the end of Falkner Street.

This project is now complete.

The Footpath Renewal Program consists of a list of footpaths which have been identified through theoretical asset management strategy, customer feedback and condition inspections carried out by staff. Council recently completed the construction of hot-mix asphalt footpath from Trevena Road to Stanley Street on the Southern side of the Kulde road.

The Seven Mile Road Upgrade project involved upgrading the section of road from the Noonameena Township to the Princes Highway. The section of road is 3.9 km long and was recently sealed from its unsealed state with improved vertical and horizontal geometry.

Council’s Kerb and Gutter Renewal Program consists of replacing concrete kerbing identified through theoretical asset management strategy, customer feedback and condition inspections carried out by staff. The renewal program for 2022/23 prioritized stage 2 of kerb & gutter replacement in Tiller Street, Tailem Bend as a continuing project from 2021/22. The project has now been successfully completed with the construction of semi-mountable kerb & gutter and driveway crossovers on the eastern side of Tiller Street.

The Wattle Street project saw the road upgraded from its unsealed state to a sealed residential street - including concrete kerbing, drainage, footpath and pram ramps installed.

Council allocated funding through the Local Roads and Community Infrastructure Program (LRCIP) and the recently adopted Footpath Expansion Program to deliver the Wattle Street upgrade.

Project construction works commenced on Monday 3rd of April 2023 and took approximately four weeks to complete.

As a part of the capital renewal of the Peake Water Supply Scheme, Council upgraded the electricity meter and pipeline from bore pump to the balance tank within the Peake Water Supply Pump Shed.

Final electrical and plumbing works occurred in early 2024.

Project Summary

With support from the Australian and State Government as well as the Meningie Progress Association, Meningie’s boat ramp jetty has been upgraded to improve accessibility and safety for recreation boating and fishing.

A new platform set at a lower height and joined to the existing jetty has been constructed to provide recreational watercrafts of varying types better access when loading people and gear from the jetty located next to the Meningie Lions Jubilee Park.

Council looks forward to residents and visitors to Meningie being able to enjoy the improved jetty facility, which is in close proximity to the main street and local shops and services.

Design of the platform addition has been carried out in collaboration with the Meningie Progress Association, who have been instrumental in working with Coorong District Council to see this project come to life.

Funding Support

Project Budget: $112,500

This project was made possible through a $67,500 Recreational Fishing, Boating and Camping Facilities Program grant, plus a $15,000 contribution from the Meningie Progress Association and support from Coorong District Council.

The Recreational Fishing, Boating and Camping Facilities Program is jointly delivered by the Australian and South Australian Governments through PIRSA, and aims to encourage South Australians to get out and enjoy the natural environment and boost regional economies.

Project Status

Construction of the jetty platform, resealing and line marking of the car park was completed in August 2023.

Meningie Lions Park Jetty Upgrade - Complete

An upgrade to the wastewater system at the Coonalpyn Swimming Pool and Caravan Park was completed late 2023.

These works saw a new septic tank and pump chamber installed to cater appropriately for the discharge from the adjacent Pool and Caravan Park amenities. A rising main was installed to shift the waste liquids to the soakage trenches which are located some distance from the facilities due to the design requirements required for the system.

The project occured in three stages to minimise impact and disruption to the Pool and Caravan Park users.

Coonalpyn Pool Wastewater Upgrade

Project Summary

Carcuma Road is a class 3 road within the Coorong District Council and is a regionally significant freight link to the Thomas Food International (TFI) Feedlot. The TFI Feedlot is a regionally significant industry generator which requires significant freight movements to operate.

The upgrade project included widening the existing road for 13km from the Dukes Highway to the end of the existing road seal at the Heinrich Road intersection, and sealing an additional 2km of Carcuma Road to provide access to the TFI Feedlot.

This project is the recipient of 2:1 funding through the Special Locals Road Program (SLRP).

Funding Support

This project has been funded through the Special Local Roads Program, the Local Roads and Community Infrastructure Program and the Coorong District Council.

Timeline

Project construction commenced in the first week of February 2023 and was completed by the end of May 2023.

The first phase of construction works included installation of culverts, widening of the road shoulders, and full road pavement construction. The second phase of the project included cement stabilisation of road shoulders, and full road construction followed by sealing.

Carcuma Road Upgrade Project

Project Summary

The Community Wastewater Management Scheme (CWMS) Renewal Program consists of a list of assets for renewal which have been identified through asset management strategy, customer feedback and condition inspections.

Council recently carried out condition assessments on all CWMS pump chambers in Tailem Bend, Wellington East, Meningie & Tintinara. Council prioritised “Urgent” and “High” category pump chambers for renewal to be delivered in two stages.

Stage 1 renewal program included five pump chambers (two in Tailem Bend and three in Meningie) from the “Urgent” category to be delivered in 2022/23. Stage 2 renewal program included nine pump chambers (six in Tailem Bend and three in Meningie) from the “High” category to be delivered in 2023/24.


Project Status - Stage 2 Complete in Tailem Bend and Meningie

Stage 2 of CWMS pump chamber renewal works commenced in August 2023 in Tailem Bend and in Meningie, and are now complete.

The project included bypassing the effluent inflow using tanker trucks to control the effluent inflows while carrying out the pump chamber relining works.

Tailem Bend Pump Station Works

Works commenced in Tailem Bend on Monday, 7 August 2023 and are complete at the following pump stations (map below):

  • Pump Station 4 - 52 Princess Highway
  • Pump Station 8 - First Avenue


Meningie Pump Station Works

Works commenced in Meningie on Monday, 28 August 2023 and are now complete at the following pump stations (map below):

  • Pump Station 5 - Narrung Road
  • Pump Station 7 - Pettett Road
  • Pump Station 4 - Warrengie DriveCommunity Wastewater Management Scheme - Renewal Program

Project Summary

Council undertakes a review of all assets each year to identify a program or renewal.

The footpath renewal program consisted of a list of footpaths which were identified through Council's asset management system and inspected on site to ascertain current condition.

This project has been funded by the Coorong District Council.

Department

Infrastructure & Assets

Footpath Renewal Program 2021/22

LocationBrief DescriptionProject Status
High Street, TintinaraFootpath replacementWas carried out in the 2021/22 Financial Year
Kulde Road, Tailem BendFootpath renewal worksThis project was a multi-year project which was completed in the 2022/23 financial year.

Community Engagement

Coorong District Council invited feedback on the draft 2022-2027 Footpath Network Expansion Strategy at the beginning of 2022. The Strategy sets the criteria and structure to guide the expansion of Council's current footpath network in a systematic and financially sustainable approach.

The final Strategy was adopted in February 2022, and includes a five-year delivery program which outlines the annual capital investment required to construct new footpaths.

Footpath Network Expansion Strategy

Footpath Renewal Program

Project Summary

Construction of Stage 2 of the Murray Coorong Trail will see it continue from where it used to end at 507 Narrung Road.

Construction of the trail continues in a south-westerly direction along the southern side of Narrung Road for 4.5kms to the Seven Mile Road intersection. The trail then continues 1.5km further down the western side of Seven Mile Road to the Coorong.

The trail has been constructed primarily on the road shoulder and adjacent road verge along property boundary fence lines within the road reserve to a width of 1.5m along Narrung Road, and a width of 1m along Seven Mile Road.

The surface of the trail is a 100mm layer of compacted limestone rubble.

Project Status

Stage Two Construction - Commenced 19 June 2023

Construction of Stage 2 of the Murray Coorong Trail commenced on Monday, 19 June 2023 and took approximately three weeks to complete.

Murray Coorong Trail