Sealed Roads Renewal Program

The 2024/25 Sealed Roads Renewal Program will undertake resealing and reconstruction on Council sealed roads which are determined to be below a satisfactory service level. The renewal program is based on the age of existing roads and their condition recorded.

Current Works

  • Hannah Well Road, Coomandook – Asphalt Overlay through Rail Crossing
  • Myrtle Place, Tailem Bend – Asphalt Cul-de-sac
  • Alison Court, Wellington East – Asphalt Cul-de-sac
  • Old Dukes Highway, Moorelands – New seal – 1 Kms
  • Pettet Street, Meningie – New seal – 0.35 Kms
  • Alexandrina Drive, Narrung – Pavement stabilisation & New seal – 4.5 Kms

Works Currently Underway

Re-seal works are planned to commence on Monday, 24th March 2025 as funded through the annual sealed roads renewal program.

Road

Suburb

Start

End

Time Frame

Hannah Well Road

Coomandook

Ashphalt overlay through rail crossing

24 - 28 March 2025

Myrtle Place

Tailem Bend

Ashpalt cul-de-sac

24 - 28 March 2025

Alison Court

Wellington East

Ashpalt cul-de-sac

24 - 28 March 2025

Alexandrina Drive

Narrung

Narrung Ferry

Start of Raukkan Township

24 March - 4 April 2025
Old Dukes HighwayMoorlands4.5 Kms South from Mallee Highway5 Kms North from Gypsm Rd Intersection31 March - 4 April 2025
Pettet Street ManingieNarrung Road IntersectionWarrengie Drive Intersection31 March - 4 April 2025

Motorists are advised that Work Zone Traffic management will be in place (with speed and lane restrictions) while the works are occurring. Members of the public are asked to be mindful of plant and personnel that will be in the area and on site.

Re-seal works are expected to take approximately three weeks to complete.

Council appreciates your understanding and patience during this time. Should you have any queries or concerns, please contact Coorong District Council on 1300 785 277.